Clarity needed on spiralling NSSO IT project set to blow past €115 million budget – John Brady TD

Sinn Féin TD for Wicklow and Chair of the Public Accounts Committee (PAC), John Brady, has called for urgent clarity and accountability over the National Shared Services Office’s (NSSO) Financial Management Shared Services (FMSS) project, amid mounting concerns that the programme is heading for a substantial overspend on its already revised €115.4 million budget.
With circ €100 million of taxpayers’ money already spent, the system remains only partially operational. Meanwhile, the latest projections indicate that the current funding allocation will be exhausted by mid-2027, despite full implementation not being expected until mid-2029.
These concerns have also been highlighted by the Comptroller and Auditor General (C&AG) in his annual report, which identified significant delays, substantial under-delivery and the absence of a clear, comprehensive plan to bring the project to completion.
Teachta Brady said:
“This project was first announced in June 2020, with an initial budget of €47 million and a target completion date of the end of 2025.
“Yet here we are, with circa €100 million spent and the system still only partially operational.
“This represents an extraordinary failure and raises very serious questions about the additional costs that will ultimately fall on the taxpayer, as well as when the project will actually be completed.
“How is it possible that such a staggering amount of public money has been spent on a system that remains incomplete and which, according to concerns being raised, is actually increasing the administrative burden on the Departments expected to use it?
“Through our work on the Public Accounts Committee, we have undertaken detailed scrutiny of major public IT projects, and what has become increasingly clear is a recurring pattern of failure, characterised by gaps in expertise, weak oversight, poor project management, inadequate initial costings and, critically, a lack of accountability when things go wrong.
“The Financial Management Shared Services project appears to demonstrate many of these same failings. 
“It has missed successive deadlines, fallen significantly short of its objectives and seen costs escalate well beyond the original budget.
“While the €115.4 million figure continues to be presented as the project's budget ceiling, we now know that this funding is expected to be exhausted by mid-2027, some two years before full implementation is projected to be completed.
“That raises a fundamental question of where will the funding come from to finish this project, and how much more will the taxpayer ultimately be expected to pay?
“The public deserves a full and transparent explanation of how a project of this scale has reached this position.
“The PAC has agreed to write to the NSSO seeking a comprehensive briefing on the Financial Management Shared Services project. 
“We want a detailed breakdown of expenditure to date, an explanation of the delays and under-delivery, an assessment of the impact on Departments, projections of any additional costs and a timeline for completion.
“Taxpayers are entitled to know where their money is going and who is accountable for delivering this project.
“We cannot continue to see major public IT projects consume vast sums of public money, repeatedly miss deadlines and fall short of what was promised without proper scrutiny, transparency and accountability.
“Ultimately, it is the public who pays the price for these failures.”